Design and Construction of Prestressed Timber Buildings for Seismic Areas

Journal

Tobias Smith, Stefano Pampanin, Massimo Fragiacomo & Andy Buchanan

A new and exciting method of timber construction has been presented. A 6-storey building design has frames in onedirection and walls in the other. Post-tensioned prefabricated LVL timber beams, columns and walls are similar sizes tothe original concrete design. Composite timber flooring is pre-fabricated. Gravity loading on the columns providesdesirable re-centering, and energy dissipaters at wall and column bases give excellent seismic behaviour.Construction will be fast with costs kept to a minimum. The overall building costs are comparable to steel and concreteoptions. Based on testing and analysis to date, the feasibility of the post tensioned hybrid solution is evident.

Volume:

16

Issue:

3

Year:

2008

Design and Construction of Prestressed Timber Buildings for Seismic Areas